Mid-Week Connection (Initialization and Binding) with New UUID
The purpose of this test is to verify that the client system can:
- recover undelivered business messages from the CME system during the mid-week initialization and binding
- adjust the inbound and outbound sequence numbers as needed
- Select a SenderComp from the drop-down and select ASSIGN if a SenderComp is not already assigned.
- From the Contracts drop-down, select the desired contract if the contract is not already locked.
- Select the START TEST button.
Note: DO NOT select the START TEST button once the test is in progress.
Note: If a test is not proceeding to the next step, selecting the Refresh button (
) below the test steps may resolve the issue.
Pre-Registered or On-Demand Format
Note: This test is used for both Pre-Registered and On-Demand formats. The image below shows the Pre-Registered format version of the test.
- To run a Mid-Week Connection (Initialization and Binding) with New UUID test:
- Over an ilink connection, submit one Limit order for a selected outright instrument.
- Receive and process an Execution Report - Confirmation/Acknowledgement Execution Report - New Order message and then submit a Terminate message or disconnect the session.
- On the same segment, submit a Negotiate message with a new UUID.
- Receive and process a Negotiate Response message.
- Submit an Establish message to bind connection.
- Select Yes or No to indicate whether your system received and processed the Establishment Acknowledgment message.
- Submit a Retransmit Request message for the undelivered Execution Report.
- Select Yes or No to indicate whether your system received and processed the Retransmission message for the undelivered Execution Report.
- Submit a Sequence message.
- Receive and process a Sequence message.